|
|
 |
FRONT PAGE
Seventy-seven
lucky lottery winners get water
By Meg
Olson
Local
property owners and developers representing nearly 500 water
connections put their names in for the recent water permit
lottery. Eighty percent of applicants came up dry.
“It was hard handing out the sad news,” said water
district commissioner Madeleine Anderson at the September 13
meeting. “Someone spit on the door.”
On September 10, a list of 77 random numbers went up on the
door of the water district office, each one corresponding to
a successful application in the district’s recent allotment
of 100 water connections (qualified as Equivalent Residential
Units, or ERUs). The district had received 420 applications
for 485 ERUs – 73 single residential applications were
allocated, one long-plat for 20 units came up lucky, and three
short plats.
“We’re drafting an acceptance letter now,” said
district manager Dan Bourks, which would notify successful applicants
by certified mail. Upon receipt of the letter, he said, successful
applicants will have 60 days to come in and pay their general
facilities fee, water connection installation charges, and a
hundred dollar fee to get a certificate of water availability,
valid for one year.
The general facilities fee is $5,500 per connection, and commissioners
approved a new resolution establishing installation charges
would be billed to recover district costs – higher if
new water lines needed to be laid or a road breached – and
the district requires a $2,150 deposit. The 20-unit long plat,
for example, needs to pay $112,000 to hold onto the ERUs allotted
to that project. A single family unit would need to pay $7,750,
a number that could go higher after water meter installation
depending on costs.
If the fees are not paid in 60 days, or the availability certificate
not submitted as part of a building or development proposal
within a year, the ERUs associated with the application are
considered available again and will go to the 23 applications
currently on a “waiting list.” If enough ERUs become
available to fill the waiting list applications, any additional
ERUs will be handed out in another allocation planned for March
2008.
To get beyond the current limited pool of water connections
it can allocate, the water system needs to upgrade its capacity,
and the district’s comprehensive plan is the roadmap.
The catch is that the state department of health did not issue
a letter of approval following its review of the water system
plan. It issued a nine-page letter enumerating 26 needed revisions. “These
comments must be adequately addressed prior to approval,” wrote
engineer John Thielmann and planner Richard Rodriguez.
“It’s a little overwhelming,” Bourks said.
An engineering meeting in Point Roberts needed to be scheduled
to have district engineers from Hammond, Collier, Wade, Livingstone
of Seattle tell commissioners why the plan they prepared had
so many holes. “We paid for an approved plan and I don’t
want to pay any more engineering fees,” Bourks said.
Bourks added some additional engineering and funding would have
to be added to move up replacement of water mains. “We’re
going to have to bite the bullet and roll some of that out with
the storage tank,” he said, explaining that they were
seeing a proliferation of water main breaks that are time consuming
to repair and pose a risk to property. ”Three breaks in
one day,” he said. “It’s killing us.”
A mechanism to fund a new storage tank proposed in the current
water system plan was included in the recent allotment. A major
infrastructure reserve of 60 connections was set aside for developers
who committed to paying for the infrastructure, to be released
to them when the new tank goes online. Bourks said funding for
new water mains would have to come from loans, grants, or ratepayers.
|