The U.S. Army Corps of Engineers released an environmental impact statement (EIS) August 12 that details the impact of operating the north wing of the BP Cherry Point shipping terminal and is awaiting consultations with local tribes before it decides whether the wing will be used as previously permitted.

In 1996, the U.S. Army Corps of Engineers approved a permit to add a north wing to the already operational south wing of the dock, originally built for ARCO in 1971. BP purchased ARCO in 2000, and construction on the north wing finished in 2001. But several environmental groups sued the Corps and BP, asking for an EIS. 

Acting as environmental group Ocean Advocates, the groups appealed when the U.S. District Court for the Western District of Washington ruled in favor of the Corps. The Ninth Circuit Court of Appeals then ordered the Corps to conduct an EIS. 

The study, which began over 15 years ago, compared the environmental risk of using the south wing dock at maximum capacity to operating out of both the north and south wing docks. Environmental groups expect shipping traffic to increase if the north wing is deemed usable, which is why they filed suit.

The groups found the originally approved permit potentially violated the Magnuson Amendment, enacted to the federal Marine Mammal Protection Act in 1977, which limits crude oil vessels in Puget Sound waters. 

The amendment prohibits federal agencies from granting permits that could “result in any increase in the volume of crude oil capable of being handled at any such facility, other than oil to be refined for consumption in the State of Washington.” The benchmark for oil volume was set October 18, 1977. 

With the release of the final EIS, the Corps will hold discussions with the Department of Justice and other third parties. EIS project manager Daniel Krenz said an anticipated decision date was set for November 12, but will likely be delayed as the Corps still has to consult local tribes. 

A Lummi Nation representative declined to comment on the decision, but said the tribe is in communication with the Corps. 

“The record of the decision will document what we are going to do with that permit,” Krenz said. 

There are three possibilities. The Corps will either propose changes to modify the existing permit, revoke the existing permit or leave the permit as is. If it decides to make changes, the Corps would bring the permit into compliance with the Magnuson Amendment, Krenz said.

The Corps is taking public comment on the EIS, which can be sent to Krenz at Daniel.A.Krenz @usace.army.mil.

In a joint press release, environmental organizations Friends of the San Juans, Evergreen Islands and Friends of the Earth said their greatest concern is that the Corps has yet to restrict the number of crude oil tankers allowed to use BP’s Cherry Point terminal. An environmental representative could not be reached for comment.

According to the EIS, the number of tanker transits increased by 226, or 27 percent, from 2000 to 2007, post construction of the north wing.

From 2008 to 2022, BP increased its daily refining capacity from 209,000 to 250,000 barrels per day, about 1.7 million gallons, according to the press release. The refinery’s capacity has increased 60 percent since its construction in 1972. 

Based on the most recent EIS data, BP’s tanker traffic declined from 2014 to 2017 with the expansion of its pipeline and rail infrastructure, but the environmental groups argue the growth in refinery and berthing capacity enables BP to increase traffic for profit.

BP Cherry Point employs more than 890 people, according to its website. Last year, it celebrated its 50th anniversary.

The EIS is available on the U.S. Environmental Protection Agency’s website and at several local libraries, including the Blaine, Ferndale and Bellingham libraries. 

Comments

2 comments on this item Please log in to comment by clicking here

  • LorraineInBlaine

    https://cdxapps.epa.gov/cdx-enepa-II/public/action/eis/details?eisId=372941

    Here's the study.

    Wednesday, September 21, 2022 Report this

  • bordergal

    Thank you,@LorraineInBlaine for posting the link to the document.

    Thursday, September 22, 2022 Report this


OUR PUBLICATIONS